Integrated Change Control

Process of reviewing all change requests, approving or rejecting them, and managing changes to deliverables, documents, and the plan.

Definition

All changes to baselines must go through this process, typically via a change control board. The impact on scope, schedule, cost, quality, and risk is assessed before a decision, and outcomes are recorded in the change log.

Example

A customer requests a new report; the PM evaluates impact, submits it to the CCB, and updates the change log.

Exam tip

Typical correct sequence: evaluate impact, submit change request, CCB decision, update plan, communicate. Never implement before approval.