Project Float

The amount of time a project can be delayed without delaying an externally imposed end date.

Definition

It exists when the critical path finishes earlier than a required finish date set by the customer or sponsor.

Example

The critical path ends June 1 and the contractual deadline is June 15: 14 days of project float.

Exam tip

Distinct from total and free float, which apply to activities.