Imposed Date

A fixed date placed on an activity or milestone, such as 'start no earlier than' or 'finish no later than'.

Definition

Imposed dates reflect contractual, regulatory, or external constraints and override network logic, which can create negative float.

Example

Regulatory filing must finish no later than December 31.

Exam tip

Imposed constraints can produce negative float in the schedule model.