Management Reserve

Budget withheld from the cost baseline for unforeseen work within project scope ('unknown-unknowns').

Definition

Using management reserve requires management approval through change control, and the cost baseline is updated when it is applied.

Example

Unexpected new regulation requires $25,000 of extra testing funded from management reserve.

Exam tip

Management reserve is not included in BAC or EVM calculations.