Budget at Completion (BAC)

The sum of all budgets established for the work to be performed.

Definition

BAC equals total planned value at project end and excludes management reserve.

Example

The cost baseline totals $250k, so BAC = $250k.

Exam tip

BAC does not change unless the baseline is changed via change control.