Precedence Diagramming Method (PDM)

Technique for constructing a schedule model in which activities are represented by nodes and linked by logical relationships.

Definition

Also known as activity-on-node (AON). It supports four relationship types: finish-to-start, start-to-start, finish-to-finish, and start-to-finish.

Example

Boxes for each activity connected by arrows showing FS relationships.

Exam tip

PDM/AON uses nodes for activities; the older arrow diagramming method (AOA) used arrows and dummy activities.