Performance Measurement Baseline (PMB)

Integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project execution.

Definition

EVM measures performance against the PMB. It excludes management reserve.

Example

EV and PV are both computed against the PMB.

Exam tip

PMB = scope + schedule + cost baselines.