ART Predictability Measure

SAFe measure comparing actual business value achieved to planned business value of committed PI objectives.

Definition

Target range is roughly 80-100%; it can exceed 100% when uncommitted objectives are achieved.

Example

Planned BV 40, actual 34: 85% predictability.

Exam tip

Uncommitted objectives can add to actual but not planned value.